March through May 2004 Progress Photos at the Route 625 (Waxpool & Church Roads) Interchange


Retaining wall progress in the interchange's Northwest quadrant. This wall will support the future Ramp E, which will carry traffic from Southbound Route 28 to Westbound Route 625.



Route 28 Southbound Collector-Distributor (C-D) Road. The Western abutment for the Route 625 bridge over Route 28 is seen in the background.


Retaining wall abutment for Ramp H Flyover Bridge, Northwest quadrant of the interchange.


In the Northeast quadrant, progress continues on the stormwater retention pond.


Storm sewer installation within the interchange's Southeast quadrant.


Forming and pouring of the center piers for the Route 625 Bridge over Route 28.