Storm sewer pipe and endwall construction in the interchange's
Northwest quadrant. Commercial Drive is shown in the background.
|
Ramp E construction, in the interchange's Northwest quadrant.
Retaining wall progress continues on both sides of the future
ramp that will carry traffic from Southbound Route 28 to Westbound
Route 625.
|
Retaining wall progress in the interchange's Northwest quandrant.
Waterline construction is shown to the right.
|
In the Northeast quadrant, progress continues on the stormwater
retention pond. Piers and abutments for the future Route
625 bridge are shown in the background.
|
Concrete deck pour for the Route 625 Eastbound Bridge over
Broad Run.
|
A completed pier and pier cap for the Ramp H Flyover Bridge.
Progress continues on median barrier for the future Westbound
Route 625.
|
Progress continues on the Western abutment for the Route
625 Bridge over Route 28.
|
Forming and pouring of the center pier caps for the Route
625 Bridge over Route 28. The completed Westbound pier cap
is shown in the foreground; the Eastbound pier cap is under
construction in the background.
|