Willard Road
July
2009
DESIGN
|
Construction
plans are approved. |
|
RIGHT-OF-WAY
|
Right
of Way acquisitions are complete. |
|
UTILITIES
|
Utility
relocations are complete. |
CONSTRUCTION
|
Placement
of aggregate subbase, asphalt and curb. Maintain erosion controll. Pour bridge decks.
Continued cut to fill and embankment activities. |
Frying Pan Road
July
2009
DESIGN
|
Construction
plans are approved. |
|
RIGHT-OF-WAY
|
Right
of Way acquisitions are complete. |
|
UTILITIES
|
Utility
relocations are complete. |
CONSTRUCTION
|
Maintain
erosion control. Pour bridge deck for SB Rt. 28 bridge widening over Horsepen Run and Ramp to EB
Frying Pan. Continued cut to fill and embankment activities. |
Nokes Boulevard
July
2009
DESIGN
|
Construction
plans are approved. |
|
RIGHT-OF-WAY
|
Right
of Way acquisitions are complete. |
|
UTILITIES
|
Utility
relocations are underway. |
CONSTRUCTION
|
Fine
grade grass areas, ditches, slopes and shoulders. Relocate utilities at Severn Way. Aggregat and asphalt
placement for Rt. 28 widening. Installation of electrical conduit system. Installation of guardrail
and fence. |
Pacific Boulevard (between Severn Way and Nokes Boulevard)
July
2009
DESIGN
|
Construction
plans are complete. |
|
RIGHT-OF-WAY
|
Right
of Way acquisitions are complete. |
|
UTILITIES
|
Utility
relocations are underway. |
CONSTRUCTION
|
Construction
is underway. |
Innovation Avenue - Phase II (Center for Innovative Technology)
July
2009
DESIGN
|
Construction
plans are complete. |
|
RIGHT-OF-WAY
|
Right
of Way acquisitions are underway. |
|
UTILITIES
|
Utility
relocations will begin concurrent with construction. |
CONSTRUCTION
|
TBD - Pending
funding availability. |
Atlantic Boulevard
July
2009
DESIGN
|
Construction
plans are under review. |
|
RIGHT-OF-WAY
|
Right
of Way acquisitions are underway.
Overview of Historic District Meeting held June 18, 2009, please
click here.
|
|
UTILITIES
|
Utility
relocations are scheduled to begin Fall 2009. |
CONSTRUCTION
|
Construction
is scheduled to begin Spring 2010. |
Air & Space Museum Parkway (formerly Barnsfield Road),
Phase II
July 2009
| The
interchange is complete and open to traffic. |
Route
625 (Waxpool & Church Roads)
July 2009
The
interchange is complete and open to traffic. |
Route
606 (Old Ox Road)
July
2009
| The
interchange is complete and open to traffic. |
Westfields
Boulevard
July
2009
| The
interchange is complete and open to traffic. |
McLearen
Road
July
2009
| The
interchange is complete and open to traffic. |
Sterling
Boulevard
July
2009
| The
interchange is complete and open to traffic. |
Loudoun County Parkway
July
2009
| The
roadway is complete and open to traffic. |
Centreville Road Widening
July
2009
| The
roadway is complete and open to traffic. |
Pacific Boulevard (between Sterling Blvd. and Cedar Green Road)
July
2009
| The
roadway is complete and open to traffic. |
Innovation Avenue - Phase I (Center for Innovative Technology)
July
2009
| The
partial interchange is complete and open to traffic. |
Braddock/Walney
July
2009
| The
intersection modifications are complete and open to traffic. |
©
Copyright 2002 Route 28 Corridor Improvements, LLC. All Rights Reserved.
|