Willard Road
July 2009

DESIGN
Construction plans are approved.
RIGHT-OF-WAY
Right of Way acquisitions are complete.
UTILITIES
Utility relocations are complete.
CONSTRUCTION
Placement of aggregate subbase, asphalt and curb. Maintain erosion controll. Pour bridge decks. Continued cut to fill and embankment activities.


Frying Pan Road
July 2009

DESIGN
Construction plans are approved.
RIGHT-OF-WAY
Right of Way acquisitions are complete.
UTILITIES
Utility relocations are complete.
CONSTRUCTION
Maintain erosion control. Pour bridge deck for SB Rt. 28 bridge widening over Horsepen Run and Ramp to EB Frying Pan. Continued cut to fill and embankment activities.


Nokes Boulevard
July 2009

DESIGN
Construction plans are approved.
RIGHT-OF-WAY
Right of Way acquisitions are complete.
UTILITIES
Utility relocations are underway.
CONSTRUCTION
Fine grade grass areas, ditches, slopes and shoulders. Relocate utilities at Severn Way. Aggregat and asphalt placement for Rt. 28 widening. Installation of electrical conduit system. Installation of guardrail and fence.


Pacific Boulevard (between Severn Way and Nokes Boulevard)
July 2009

DESIGN
Construction plans are complete.
RIGHT-OF-WAY
Right of Way acquisitions are complete.
UTILITIES
Utility relocations are underway.
CONSTRUCTION
Construction is underway.


Innovation Avenue - Phase II (Center for Innovative Technology)
July 2009

DESIGN
Construction plans are complete.
RIGHT-OF-WAY
Right of Way acquisitions are underway.
UTILITIES
Utility relocations will begin concurrent with construction.
CONSTRUCTION
TBD - Pending funding availability.


Atlantic Boulevard
July 2009

DESIGN
Construction plans are under review.
RIGHT-OF-WAY
Right of Way acquisitions are underway.
Overview of Historic District Meeting held June 18, 2009, please click here.
UTILITIES
Utility relocations are scheduled to begin Fall 2009.
CONSTRUCTION
Construction is scheduled to begin Spring 2010.


Air & Space Museum Parkway (formerly Barnsfield Road), Phase II
July 2009


The interchange is complete and open to traffic.


Route 625 (Waxpool & Church Roads)
July 2009


The interchange is complete and open to traffic.



Route 606 (Old Ox Road)
July 2009

The interchange is complete and open to traffic.


Westfields Boulevard
July 2009

The interchange is complete and open to traffic.


McLearen Road
July 2009

The interchange is complete and open to traffic.


Sterling Boulevard
July 2009

The interchange is complete and open to traffic.


Loudoun County Parkway
July 2009

The roadway is complete and open to traffic.


Centreville Road Widening
July 2009

The roadway is complete and open to traffic.


Pacific Boulevard (between Sterling Blvd. and Cedar Green Road)
July 2009

The roadway is complete and open to traffic.


Innovation Avenue - Phase I (Center for Innovative Technology)
July 2009

The partial interchange is complete and open to traffic.


Braddock/Walney
July 2009

The intersection modifications are complete and open to traffic.