FALL 2015 UPDATES


Pacific Boulevard Extension - Phase 3


DESIGN
Complete.
RIGHT-OF-WAY
Underway.
UTILITIES
Underway.
CONSTRUCTION
Scheduled to complete Summer 2016.


Pacific Boulevard Extension - Phase 4


DESIGN
Complete.
RIGHT-OF-WAY
Complete.
UTILITIES
Complete.
CONSTRUCTION
Scheduled to complete Summer 2016.


Innovation Avenue - Phases 2 & 3 (Center for Innovative Technology)


DESIGN
Construction plans are complete.
RIGHT-OF-WAY
Complete.
UTILITIES
Complete.
CONSTRUCTION
Construction is underway. Scheduled for completion end of 2016


IRoute 28: 8-Lane Widening Areas 1, 2 & 3


DESIGN
Complete.
RIGHT-OF-WAY
Underway.
UTILITIES
Underway.
CONSTRUCTION
Construction is underway. Scheduled to complete Spring 2017.




Belfort Park Area Road Improvements


The roadway is complete and open to traffic.


Pacific Boulevard Extension - Phase 2


The roadway is complete and open to traffic.


Route 28 Bridge Widening Over Dulles Toll Road


Bridge widening is complete.


Atlantic Boulevard


The interchange is complete and open to traffic.


Frying Pan Road

The interchange is complete and open to traffic.

Nokes Boulevard

The interchange is complete and open to traffic.

Willard Road

The interchange is complete and open to traffic.


Air & Space Museum Parkway (formerly Barnsfield Road), Phase II

The interchange is complete and open to traffic.

Route 625 (Waxpool & Church Roads)

The interchange is complete and open to traffic.


Route 606 (Old Ox Road)

The interchange is complete and open to traffic.


Westfields Boulevard


The interchange is complete and open to traffic.


McLearen Road

The interchange is complete and open to traffic.


Sterling Boulevard

The interchange is complete and open to traffic.


Loudoun County Parkway

The roadway is complete and open to traffic.


Centreville Road Widening

The roadway is complete and open to traffic.


Pacific Boulevard (between Sterling Blvd. and Cedar Green Road)

The roadway is complete and open to traffic.


Innovation Avenue - Phase I (Center for Innovative Technology)

The partial interchange is complete and open to traffic.


Braddock/Walney

The intersection modifications are complete and open to traffic.


Pacific Boulevard (between Severn Way and Nokes Boulevard)

The roadway is complete and open to traffic.